unofficially, the project is 3 months behind. 2 issues...
Posted on: July 20, 2019 at 14:29:29 CT
GapDaddy MU
Posts:
16515
Member For:
25.07 yrs
Level:
User
M.O.B. Votes:
0
1. Engineering did not adequately or accurately identify the dis-uniformity of the old landfill that was the area south of the old south stands. Drilling for the pylons took at least 60 days longer than anticipated and delayed the start of crane work.
2. This last winter was the worst winter for ground work in mid missouri in the last 30 years. Shelter Insurance on Broadway is 9 months behind schedule on a much smaller project so because of lost days.